5C Data Centers is advancing the MEM01 data center at 4300 Getwell Road in Memphis, Shelby County, Tennessee. A Phase IV commercial alteration permit filed October 6, 2026, covers approximately 504,000 square feet of the former Fred's headquarters and distribution complex and carries a stated permit value of $575 million, first reported by Local Memphis and picked up by the Daily Memphian and Data Center Frontier.
What was filed
A Phase IV commercial alteration permit application, still under review as of the filing date, targeting a major build-out of an existing industrial complex already in partial data-center operation.
| Detail | Filed or reported figure |
|---|---|
| Permit application date | October 6, 2026 |
| Permit scope | Phase IV commercial alteration |
| Area covered by permit | ~504,000 sq ft |
| Stated permit value | $575 million |
| Total property size | ~1.1 million sq ft |
| Current operating footprint | ~200,000 sq ft |
| Reported current capacity | ~20 MW |
| Target capacity | up to 84 MW |
| MLGW-approved additional compute power | 9 MW |
| Further MLGW request (not yet approved) | ~50 MW |
| Site acquisition price | $25 million |
No named tenant was identified in available reporting, and no final approval date has been established.
Who 5C Data Centers is
5C Data Centers, operating under the 5C Group, is an Ohio-based developer focused on large-scale AI infrastructure. MEM01 is its Memphis campus, built inside the former Fred's retail headquarters and distribution complex. The project is notable for its behind-the-meter power strategy: rather than relying entirely on Memphis Light, Gas and Water, 5C is pursuing fuel-cell and other on-site generation to reach its 84 MW target.
Why Memphis, and why now
- β’The building was already there. Acquiring 1.1 million square feet of industrial shell for $25 million gave 5C a cost basis that purpose-built campuses cannot match. The retrofit path is slower than a greenfield shell, but the economics of land and structure are hard to replicate in primary markets.
- β’AI infrastructure is driving demand for large, contiguous power blocks. Operators building AI factories need density and the ability to expand without moving sites. A 1.1-million-square-foot complex under single ownership provides that runway.
- β’Behind-the-meter generation is emerging as a primary strategy, not a backup. Rather than waiting on utility queue approvals for 50 MW or more, 5C is engineering around the grid constraint using fuel cells. MLGW has confirmed approval for 9 MW of infrastructure supporting additional compute power, but the larger 50 MW request remained pending as of October 6, 2026.
- β’Memphis sits at a logistics crossroads. Industrial electrical and mechanical talent, established by decades of warehousing, manufacturing, and distribution, is concentrated here in a way that suits a retrofit of this type.
When a utility queue is too slow for an AI deployment timeline, fuel-cell generation becomes a critical-path infrastructure decision, not an add-on.
Power strategy and what it signals
The 84 MW target, if reached entirely through behind-the-meter sources, would make MEM01 one of the more aggressive applications of non-grid primary power in the region. The MLGW situation is instructive: the utility confirmed 9 MW of approved infrastructure while a further 50 MW request remained open. That gap is what the fuel-cell strategy is designed to bridge. For operators watching Memphis as a potential market, the takeaway is that utility approval timelines in mid-tier cities can be as constraining as in primary markets, and that the developers moving fastest are the ones arriving with a generation plan that does not depend entirely on grid interconnection.
What it means for the region's labor market
A 504,000-square-foot alteration permit at a live industrial site is not a conventional data-center construction project. Trades demand here skews toward industrial electrical, mechanical systems, controls, and retrofit project management, roles that Memphis already supplies in depth from its logistics and manufacturing base. The non-obvious staffing pressure, however, is in power generation: the fuel-cell and behind-the-meter systems require controls engineers, commissioning technicians, and industrial-maintenance specialists who sit at the intersection of utility and data-center expertise. That profile is scarcer than a commercial electrician, and employers across the Memphis metro, from FedEx operations to heavy manufacturing, compete for the same hands. Operators and contractors building out MEM01 or supplying into its supply chain will need a deliberate sourcing strategy for that tier of talent. We break down roles, pay, and where the talent is in our guide to hiring data center talent in Memphis, Shelby County.
Sources: Local Memphis, which first reported the filing, the Daily Memphian, and Data Center Frontier.
Have a data center role to fill?
Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.
Read More Blog Posts
Hiring Data Center Talent in Memphis for 5C Data Centers' MEM01 Expansion
Memphis is about to have a data center hiring problem with an unusual twist. 5C Data Centers filed a Phase IV commercial alteration permit in October 2026 covering approximately 504,000 square feet at the former Fred's h
Hiring Data Center Talent in Augusta, GA: Roles, Pay, and Where the People Actually Are
Augusta is about to have a data center hiring problem. 3G Investments filed rezoning applications in September 2026 for the Nixon Technology Campus, a proposed seven-building, 3.34-million-square-foot campus on 383 acres