Amazon is developing Project Spectrum, a large-scale data center campus on approximately 435 acres adjacent to the Comanche Peak Nuclear Power Plant in unincorporated Somervell County, near Glen Rose, Texas. The project was first reported by Amazon's own news team and covered further by the Amazon Press Center and Crypto Briefing.
What was filed
Amazon Data Services filed plans for a campus that would draw up to 1,200 megawatts from Comanche Peak under a 20-year power agreement with Vistra Corp., which owns both the plant and the roughly 435 acres where the campus will be built. Local approvals were reported as completed in February 2026, and site preparation is already underway.
| Detail | Planned figure |
|---|---|
| Site area | ~435 acres |
| Buildings | Up to 18 |
| Power agreement | Up to 1,200MW, 20-year term |
| Power source | Comanche Peak Nuclear Power Plant |
| Investment | ~$5 billion |
| Initial energization | 2027 |
| Full delivery target | Q4 2027 |
| Full ramp-up | 2032 |
| Permanent jobs | At least 550 full-time positions |
Electricity will travel from Comanche Peak through dedicated transmission lines to an on-site substation, with Amazon paying the full energy cost. Cooling water will come from the Comanche Creek industrial reservoir through surface-water rights leased from Vistra, keeping the project off local groundwater and municipal drinking-water supplies.
Who Amazon is
Amazon Web Services is the cloud infrastructure arm of Amazon, one of the largest hyperscale operators in the world by installed capacity. Project Spectrum represents one of its most direct power-procurement arrangements to date: a bilateral, long-term agreement tying a single campus to a single nuclear generating source rather than relying on grid-averaged power.
Why Somervell County, and why now
- β’A stranded nuclear asset became a hyperscale opportunity. Comanche Peak has firm, dispatchable, carbon-free generation capacity and the land to co-locate a buyer directly on its fence line. That combination is rare at any scale.
- β’The power agreement sidesteps grid congestion entirely. Dedicated transmission lines to an on-site substation mean Project Spectrum does not compete with other ERCOT load for interconnection queue position or transformer availability.
- β’AI workloads are accelerating demand for always-on power. Large language model inference and training require sustained, non-interruptible electricity that nuclear is uniquely suited to provide, and hyperscalers are increasingly willing to sign decade-scale contracts to secure it.
- β’Vistra needed an anchor customer for a stranded land position. The 435-acre parcel adjacent to an operating plant has limited alternative uses, making a 20-year lease and power agreement mutually attractive.
When a hyperscaler can connect directly to a nuclear plant on private land, it eliminates three of the most common large-campus bottlenecks simultaneously: grid interconnection, power price volatility, and carbon accounting.
Infrastructure and water
The water strategy deserves attention from anyone planning a comparable campus. By leasing industrial surface-water rights from Vistra's Comanche Creek reservoir, Amazon avoids drawing on local groundwater or municipal systems, a structurally important choice in a small rural county where community water supply is a sensitive political issue. That approach may have been a meaningful factor in securing local approvals ahead of a project of this scale.
What it means for the region's labor market
A campus of this size, built in phases through 2032, will generate thousands of construction jobs and at least 550 permanent operations positions in a county whose existing industrial workforce is almost entirely tied to Comanche Peak itself. That nuclear plant workforce, electricians, instrument and controls technicians, mechanical maintenance personnel, and outage contractors, is the closest available pool of high-reliability industrial talent. The challenge is that Comanche Peak's refueling and maintenance outage cycles can pull those same workers away from data center commissioning work at precisely the moments when Project Spectrum needs them most.
The Dallas-Fort Worth metro, roughly 50 miles northeast of Glen Rose, is the deepest regional source of electricians, pipefitters, controls technicians, equipment operators, and data center contractors. DFW's own infrastructure and semiconductor pipeline is already creating significant competing demand for that labor pool, so employers and subcontractors planning work at Project Spectrum should expect to source talent from a wide radius and plan schedules around Comanche Peak's outage calendar. For a detailed breakdown of roles, pay ranges, and where the talent is sourced, see our guide to hiring data center talent in Somervell County, Texas. Sources: Amazon's news team, which first reported the project details, the Amazon Press Center, and Crypto Briefing.
Have a data center role to fill?
Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.
Read More Blog Posts
Hiring Data Center Talent in Glen Rose, TX: Roles, Pay, and Where the People Actually Are
Amazon is building one of the most unusual data center campuses in the country. Project Spectrum, a planned 18-building, $5 billion campus on roughly 435 acres adjacent to Comanche Peak Nuclear Power Plant in Somervell C