CRG, the St. Louis-based data center development arm of Clayco, is proposing a 600MW hyperscale campus on roughly 360 acres in Festus, Jefferson County, Missouri. The project was first reported by Leader Publications (My Leader Paper) and is tracked by SUE Data Centers and SAVRN.
What was approved
The Festus City Council voted 6-2 on March 30, 2026, to approve a development agreement for the campus. A follow-on vote of 5-2 on August 24, 2026, annexed three additional parcels totaling about 6.55 acres, bringing the full site under city jurisdiction. The project carries a permitted status in public trackers, though no building permit or construction plan had been submitted to the city as of June 12, 2026.
| Detail | Figure |
|---|---|
| Site area | ~360-361 acres |
| Planned capacity | 600MW |
| Estimated project cost | US$6 billion |
| Projected city/district fiscal impact | ~$1.3 billion total; up to $80M per year |
| Development agreement vote | 6-2, March 30, 2026 |
| Annexation vote | 5-2, August 24, 2026 |
| Power utility | Ameren (power study underway) |
CRG's model for this project is developer-led: CRG will build the campus and subsequently hand operations to a tenant operator. No operating tenant has been named in public records.
Who CRG is
CRG is the data center development arm of Clayco, a full-service real estate, architecture, engineering, and construction firm headquartered in St. Louis. The structure means CRG can self-perform significant portions of the development process, from design through construction, before transferring the asset to an operator. That vertical integration is a meaningful factor in how the Festus campus will be staffed and sequenced.
Why Festus, and why now
- β’Land at scale is increasingly hard to find near primary markets. A 360-acre contiguous site with highway access north of Highway 67 and west of Highway CC is a rare greenfield footprint within the broader Midwest industrial corridor.
- β’The transmission infrastructure is workable. Ameren is already conducting a power study for the site, signaling that the utility-side conversation is active even before entitlements are fully resolved.
- β’Jefferson County has industrial land economics. Compared to Northern Virginia or Phoenix, per-acre acquisition and development costs remain favorable, and the county's history of large-footprint industrial and energy-intensive facilities means the site-prep ecosystem already exists.
- β’Missouri is drawing hyperscale attention broadly. Competing projects such as the Nebius AI campus in Independence signal that Missouri's grid, land, and incentive environment is attracting developers who have looked past saturated coastal and Sun Belt markets.
When a developer with in-house construction capacity controls a site of this scale near established transmission, the entitlement vote is less a finish line than a starting gun for trade mobilization planning.
Ameren and the power path
Ameren's power study is the critical near-term variable. A 600MW campus requires a purpose-built or heavily upgraded interconnection, and the timeline from study completion to energization on a project of this scale typically runs several years. The absence of a disclosed interconnection agreement means the construction schedule remains contingent on Ameren's findings. For workforce planners, this is the clock to watch: substation and transmission crews will need to be lined up well ahead of the first building shell.
Local reception
The project faces active legal opposition. Citizen group Wake Up JeffCo and several property owners filed a Sunshine Law suit in early April 2026 seeking to void both the rezoning and the development agreement. The suit argues that procedural requirements were not met during the approval process. As of mid-2026, that litigation remains pending, meaning the project's land-use and contractual status is not fully settled despite the council votes. The 6-2 and 5-2 approval margins suggest council support is real but not unanimous, and the annexation step drew its own dissent.
What it means for the region's labor market
A 600MW campus built in phases across 360 acres is among the largest single construction commitments the Jefferson County labor market has ever been asked to absorb. The St. Louis metro has deep union building-trades capacity across electrical, ironwork, carpentry, and operating engineers, built over decades of heavy industrial and manufacturing work along the Mississippi River corridor. That base is well-suited to the substation, civil, and structural phases of a hyperscale build.
The complication is timing and competition. Other large Missouri data center and industrial projects are drawing from the same pool of electricians, HVAC technicians, and civil trades, and peak phases will overlap. More specifically to Festus, CRG's developer-then-operator model, combined with the ongoing Sunshine Law litigation, creates genuine uncertainty about when mobilization begins. Trades that commit early to other regional projects may not be available when Festus finally breaks ground. The practical implication is that general contractors and specialty subcontractors who want a position on this campus should be building those relationships now, not after a permit is pulled.
For a full breakdown of roles, pay bands, and where the qualified talent sits, see our guide to hiring data center talent in Jefferson County, Missouri. Sources: Leader Publications (My Leader Paper), which first reported on the project's community engagement, with additional tracking data from SUE Data Centers and SAVRN.
Have a data center role to fill?
Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.
Read More Blog Posts
Hiring Data Center Talent in Festus, Missouri: Roles, Pay, and Where the People Actually Are
CRG is proposing a 600 MW hyperscale campus on 360-plus acres in Festus, Jefferson County, and the talent that facility will eventually need is not waiting around in Jefferson County.
Hiring Data Center Talent in Lower Mount Bethel Township, PA: Roles, Pay, and Where the People Actually Are
Lower Mount Bethel Township is about to have a data center hiring problem. Talen Energy, Peron Development, and J.G.