Eatonton 379 LLC Files for a 520MW, 11-Building Data Center Campus in Putnam County, Georgia

Eatonton 379 LLC Files for a 520MW, 11-Building Data Center Campus in Putnam County, Georgia

Oct 29, 20264 min readBy Matthew Taksa

Eatonton 379 LLC filed a Development of Regional Impact (DRI) application with the Georgia Department of Community Affairs on October 26, 2026, for a proposed data center campus in unincorporated Putnam County near Eatonton. The filing, first reported by Data Center Dynamics and also covered by Colocation Scout and Construction Review Online, describes a campus of up to 11 buildings on approximately 542 acres along Glenwood Springs Road, with a peak connected load of up to 520MW and an estimated value of $3.5 billion at build-out.

What was filed

The DRI submission describes a greenfield campus on 542 acres, with local rezoning and conditional-use approvals still pending. No construction, energization, or final project approval had been granted as of available reporting.

DetailFiled figure
Site area~542 acres
BuildingsUp to 11
Total floor area~3.5 million sq ft
Peak connected loadUp to 520MW
Estimated value at build-out~$3.5 billion
Anticipated completion2031
Potential electricity suppliersTri-County EMC or Georgia Power

No utility agreement has been announced, and no tenant or ultimate investor has been publicly identified.

Who Eatonton 379 LLC is

Eatonton 379 LLC is the project entity named in the DRI filing. No parent company, operator, or end-user tenant has been disclosed in available reporting. The LLC name reflects the site's address corridor rather than an established data center brand, which is consistent with how early-stage land-control vehicles are often structured before a developer or hyperscaler steps forward publicly.

Why Putnam County, and why now

  • β€’
    Georgia's grid and incentive environment remain competitive. The state has attracted sustained hyperscale interest, and both Georgia Power and Tri-County EMC serve this corridor, giving a project optionality on the utility side even without a signed agreement.
  • β€’
    Land availability outside Atlanta is the constraint being solved. Northern Georgia and the Atlanta metro are absorbing demand at a pace that is pushing developers to look at adjacent rural counties where large, contiguous acreage can still be assembled.
  • β€’
    The 542-acre greenfield gives room to phase. An 11-building program at this scale implies sequential delivery over several years, which aligns with the 2031 target and reduces the risk of committing to a single large energization event before utility capacity is confirmed.
  • β€’
    The DRI process signals regional significance. Georgia's DRI threshold triggers review when a project is large enough to affect multiple jurisdictions, meaning the state has already acknowledged the campus as a regionally material development.
πŸ”‘Key takeaway

When a rural county sits within reach of an established utility grid and a major metro labor pool, a single large land assembly can unlock a campus-scale filing even before a named operator is attached.

Infrastructure considerations

The absence of a confirmed utility agreement is the critical open variable. With up to 520MW of peak connected load, this campus would require transmission-level infrastructure additions regardless of whether Tri-County EMC or Georgia Power ultimately serves it. The DRI filing notes possible on-site generation, which suggests the developer is already modeling scenarios where utility delivery alone may not satisfy the full load on the preferred timeline. Putnam County's active moratorium on data center permits, extended through November 17, 2026, adds a regulatory dependency that must clear before any construction timeline becomes meaningful. The 2031 completion target assumes that rezoning, utility agreements, and permitting all resolve on a compressed schedule for a project of this complexity.

Local reception

Putnam County extended a moratorium on data center permits through November 17, 2026, which was in effect at the time of the DRI filing. The moratorium reflects the county's need to assess whether its zoning framework and infrastructure capacity are suited to a campus of this scale before approving new permits. The project had not received local zoning or conditional-use approval as of available reporting.

What it means for the region's labor market

Putnam County does not have an established data center workforce or a union construction presence tied to this sector. Eatonton sits approximately 74 miles southeast of Atlanta, which makes the Atlanta metropolitan area the practical source for the specialized trades this campus would require: high-voltage electrical, mechanical systems, controls, and commissioning crews with hyperscale experience. General construction labor and logistics capacity can be drawn more locally, but the critical-path disciplines will need to be recruited and in many cases relocated from Atlanta or beyond. At 520MW across 11 buildings, construction demand will arrive in waves over multiple years, creating sustained rather than one-time hiring pressure across both categories. For a detailed breakdown of roles, pay ranges, and where the talent sits, see our guide to hiring data center talent in Eatonton, Putnam County, Georgia.

Sources: Data Center Dynamics, which first reported the filing, and Colocation Scout and Construction Review Online.

Have a data center role to fill?

Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.

Read More Blog Posts

Eatonton 379 LLC Files for a 520MW, 11-Building Data Center Campus in Putnam County, Georgia