Google is about to create a concentrated data center hiring problem in Tulsa County. Beale Infrastructure is developing the hyperscale campus known as Project Clydesdale on 506 acres just west of Owasso, and Google publicly confirmed in August 2026 that it will operate the facility as part of its global network. Construction is already underway. With at least four phases planned at $700 million or more per phase, the staffing demand that follows will be large, sustained, and competitive in ways the Tulsa metro has not seen concentrated in a single location before.
Data center hiring comes in three waves
- β’Construction and trades, first. Civil, structural, mechanical, and electrical crews carry the campus through the building envelope and distribution infrastructure. Tulsa metro has deep trade capacity here.
- β’Commissioning, the pressure point. A narrow band of engineers who know how to test, verify, and sign off on critical systems before a hyperscale operator accepts a building. These people are national, not local, and they are already stretched thin across the country.
- β’Operations, for the life of the building. Critical facilities engineers and technicians who run the campus day in and day out. Google builds long-term, which means these roles are permanent, not project-based.
The construction wave is a Tulsa trades problem. Commissioning and operations are national recruiting problems that happen to land in Oklahoma.
What these roles pay in 2026
| Role | Average base | Typical range |
|---|---|---|
| Commissioning engineer | ~$147,000 | $84,000 to $196,000 |
| Critical facilities engineer | ~$132,000 | $117,000 to $147,000 |
| Critical facilities technician | ~$89,000 | $75,000 to $105,000 |
| Facilities technician (entry) | ~$54,000 | $42,500 to $77,000 |
Google's compensation philosophy runs toward the top of these bands in major markets. Owasso is not a major market, but the operator is Google, which typically holds internal comp bands regardless of geography.
The certifications and background that actually matter
For commissioning engineers, look for candidates who have completed functional performance testing on chilled water plants, medium-voltage switchgear, and UPS systems at hyperscale scale. ASHRAE Commissioning Process Management Professional (CPMP) or equivalent third-party credentials matter, but documented hours on large-scale data center turnover matter more. For critical facilities engineers and technicians, prior experience inside an active Tier III or Tier IV environment is the real filter. Certifications that carry weight include BICSI DCDC, Uptime Institute Accredited Tier Designer, and any OEM training from Schneider, Eaton, or Vertiv on the specific UPS and PDU lineups a candidate has operated. OSHA 30 is a baseline expectation across all roles, and high-voltage switching experience with documented qualifications is increasingly required for senior technician roles.
Google's background check standards are thorough, so candidates with gaps in employment documentation or unresolved security issues will not clear screening regardless of technical qualifications.
How to structure the offer
Commissioning engineers are almost always contractors working project-to-project. Per diem plus a daily or weekly rate is the expected structure. Travel reimbursement to a home airport on a defined rotation is standard. Trying to convert these candidates to permanent roles mid-project rarely works and often causes attrition. Critical facilities engineers and technicians for the operations team are permanent hires. Relocation packages for candidates coming from outside Oklahoma are worth building into the offer because the local bench for experienced operators is thin. A lump-sum relocation of $5,000 to $15,000, depending on distance, is realistic for operators hiring at this scale.
For commissioning, compete on total comp and rotation schedule; for operations, compete on base salary, relocation, and the stability of a Google-operated campus.
Where each role actually gets sourced
Commissioning engineers come from a national pool of people who move from project to project. They are active on LinkedIn, they are known to commissioning-focused staffing firms, and they frequently surface through referrals within the commissioning community. Posting to general job boards produces low signal for this role. Critical facilities engineers with hyperscale experience are concentrated in Northern Virginia, Phoenix, central Iowa, and along the established Google corridor. Many are open to relocation if the campus is stable and the operator is recognizable. Google's brand helps here. Critical facilities technicians can sometimes be sourced regionally from candidates who have worked in industrial control, power distribution, or HVAC maintenance in heavy-industry environments and are willing to cross-train into data center operations. The Tulsa refinery and manufacturing base produces workers with relevant mechanical and electrical skills. Construction trades are sourced locally through Tulsa IBEW, UA pipefitters, and the broader Green Country building trades network. The demand, however, will outpace local supply on high-voltage and large mechanical scopes.
The Owasso reality: strong on trades, thin on hyperscale operators
The non-obvious problem here is not labor scarcity in the abstract. It is concentration. Google's existing campus in Pryor, Project Clydesdale in Tulsa County, and Project Mustang in nearby Rogers County are all pulling from the same regional pool at roughly the same time. The Green Country corridor is becoming an emergent hyperscale cluster, which is good news for long-term depth but creates an acute short-term squeeze on the specific workers who have already completed one or more hyperscale projects. Tradespeople with prior experience on high-voltage substations and large-scale mechanical systems for data centers are being competed for by multiple operators and general contractors simultaneously. Whoever reaches that narrow slice of the regional trade workforce first, and makes a credible commitment on schedule and rate, will staff up. Everyone else will be managing gaps through the commissioning window.
The timeline is the hiring plan
Construction started in fall 2025 and is reported as active. Phase 1 completion is targeted for Q3 2027, with Phase 2 construction starting Q1 2027. That overlap between phases is where hiring pressure compounds. Commissioning engineers need to be identified and committed before the building envelope closes on Phase 1, which means sourcing for those roles is not a 2027 problem. It is happening now. Operations hiring for the initial team typically starts six to nine months before a building goes live, putting that search in late 2026 or early 2027 for Phase 1.
The phased structure means this is not a single hiring event but a multi-year recruiting commitment, and the operations headcount will grow with each phase that comes online.
How NextDCX helps
NextDCX recruits for your toughest data center roles. Share the work, location, and experience your team needs. We run a fresh search for every role, approach people directly, and speak with every candidate before introducing them. You get people screened for the work, pay, location, and availability, ready to meet your hiring team. We also support recruiting partners. If Project Clydesdale roles are on your board, whether that is commissioning now or operations ahead of the Phase 1 go-live, send us the reqs and we start sourcing today.
For the full campus details, see Google's Tulsa County Project Clydesdale filing.
Comp sources: ZipRecruiter and dcgeeks 2026 salary data.
Have a data center role to fill?
Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.
Read More Blog Posts
Fredericksburg City Council Votes 7β0 to Reject Penzance Development's 1500 Gateway Data Center Campus
Penzance Development, through its affiliate 1500 Gateway LLC, sought to build a roughly 1-million-square-foot data center campus on 83β84 acres of the Hylton Tract in Fredericksburg, Virginia, near Interstate 95.
Google Confirms It Will Operate the 506-Acre Project Clydesdale Campus in Tulsa County, Oklahoma
Google publicly announced on August 19, 2026 that it will operate a hyperscale data center campus in unincorporated Tulsa County, Oklahoma, as part of its global network.