NextDCX

NextDCX

Riot Platforms Files a $400M Building and Signs a 910MW Powered-Land Lease at Its Corsicana Campus

Riot Platforms Files a $400M Building and Signs a 910MW Powered-Land Lease at Its Corsicana Campus

Nov 15, 20264 min readBy Matthew Taksa

Riot Platforms has filed plans with the Texas Department of Licensing and Regulation for a new data center building at its existing campus at 6980 FM 709 in Corsicana, Navarro County, Texas, while separately announcing a 910MW powered-land lease with an unnamed frontier AI laboratory. The building filing was first reported by Data Center Dynamics; the lease was covered by Data Center Dynamics, Data Center Frontier, and Yahoo Finance.

What was filed

The TDLR filing, identified as Project Ditto, covers a two-story data center building totaling 335,430 square feet. Reported development cost is $400 million, with construction scheduled from April 2026 through May 2028.

DetailFiled figure
Building count1 (two-story)
Total floor area335,430 sq ft
Reported development cost$400 million
Construction startApril 2026
Construction completionMay 2028

The filing is a state-level TDLR registration. No city or county planning approval, building permit, or utility interconnection approval beyond that filing has been confirmed in available sources.

Who Riot Platforms is

Riot Platforms is a Bitcoin-mining and digital-infrastructure company whose Corsicana campus already carries 400MW of operational power capacity for Bitcoin mining, with long-term development plans reaching approximately 1GW across the site. The campus is therefore an operating high-voltage industrial facility, not a greenfield conversion, which has practical consequences for how construction and operations talent are recruited.

Why Corsicana, and why now

  • β€’
    The power was already built. A site with 400MW in service and a credible path to 1GW does not require years of transmission-queue negotiations; the foundational electrical infrastructure is a sunk asset.
  • β€’
    The lease terms fit AI infrastructure timing. The 15-year triple-net powered-land lease covering 910MW of IT capacity is structured in three phases: 400MW in September 2027, 200MW in January 2028, and 310MW in July 2028. That schedule aligns with the compressed deployment timelines frontier AI operators are demanding.
  • β€’
    Frontier AI demand is running ahead of greenfield supply. Secondary reporting identifies Anthropic as the first tenant under the lease, though that identification has not been confirmed by the TDLR filing itself. What the lease terms do confirm is that Riot supplies land, powered pads, and electrical infrastructure while the tenant supplies and operates its own computing equipment, a structure that lets an AI operator skip site-development risk entirely.
πŸ”‘Key takeaway

Repurposed or co-located power assets are compressing the development timeline that would otherwise separate an AI operator from a live data center.

The infrastructure scale now on the table in Corsicana

The combined picture at the Corsicana campus is large even by hyperscale standards. The 332-acre contiguous site and 910MW lease commitment sit alongside the existing 400MW Bitcoin-mining load and the separately filed 335,430-square-foot building. If the long-term 1GW development target is realized, Corsicana becomes one of the largest single-campus power commitments in the American interior. That scale is not a function of Corsicana's size as a city; it is a function of what Riot already built there.

What it means for the region's labor market

A phased 910MW delivery schedule beginning in September 2027, combined with a $400 million building under construction from April 2026, creates a sustained multi-year demand surge for specialized trades and technical staff rather than a single hiring spike.

Corsicana sits roughly 50 miles southeast of Dallas, which puts the site within range of the Dallas-Fort Worth construction and electrical-trades labor pool. That proximity helps for general construction headcount. The harder constraint is specialized high-voltage and commissioning labor: the crews who energize switchgear, test protection relays, and commission large UPS and generator strings are under sustained pressure across the full Dallas-Fort Worth to Central Texas corridor, and demand from this campus will compete directly with every other large project in that corridor.

One non-obvious advantage is that the existing Bitcoin-mining campus likely carries some onsite and contractor-network experience in high-voltage operations, controls, security, and maintenance. That existing knowledge base is a recruiting asset, but it does not close the gap for the volume of commissioning engineers and critical-facilities technicians a 910MW phased buildout requires. Roles in highest demand across a project of this scale include commissioning engineers (median total compensation around $147,000 in the Texas market), critical facilities technicians (around $89,000), construction electrical foremen, and high-voltage protection and controls specialists. Operations staffing for a facility of this size typically runs into the hundreds of full-time employees across shifts once all phases are energized. We break down roles, pay, and where the talent is in our guide to hiring data center talent in Navarro County. Sources: Data Center Dynamics, which first reported the TDLR building filing, with additional coverage from Data Center Dynamics, Data Center Frontier, and Yahoo Finance.

Have a data center role to fill?

Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.

Read More Blog Posts