Iron Mountain Data Centers is developing the Richmond Data Center Campus at White Oak Technology Park in Sandston, Henrico County, Virginia, a 66-acre, federally compliant colocation campus planned for more than 200 MW of total power capacity and well over one million square feet across four buildings. The project was first reported by Iron Mountain's own facility pages and picked up by Data Center Dynamics and Data Center Knowledge.
What was filed and announced
Iron Mountain has acquired the 66-acre White Oak Technology Park site and publicly detailed two buildings, with construction on the first underway by August 2026 and a billion-dollar total investment cited across the full campus.
| Detail | Announced figure |
|---|---|
| Total site | 66 acres |
| Buildings planned | 4 (RCH-1 through RCH-4) |
| Total campus capacity | 200+ MW |
| Total colocation space | Well over 1 million sq ft |
| Total investment | Over $1 billion |
| RCH-1 capacity | 48 MW |
| RCH-1 size | 364,860 sq ft |
| RCH-1 workload focus | AI inferencing and cloud |
| RCH-3 capacity | 60 MW |
| RCH-3 size | ~440,000 sq ft |
| RCH-3 data halls | 6 |
| RCH-3 first availability | Q3 2028 (August 2028 - April 2029 phased) |
| Power matching | 100% renewable |
Who Iron Mountain is
Iron Mountain began as a records management company and has grown into a global REIT operating data centers across North America, Europe, and Latin America. Its data center division positions itself squarely at the intersection of colocation and federal compliance, holding certifications that most commercial operators do not pursue. The Richmond campus is designed to meet FISMA HIGH, FedRAMP, and NIST 800-53 requirements, making it one of the more stringent compliance environments currently under construction in the mid-Atlantic region.
Why Henrico County, and why now
- β’Northern Virginia is constrained. Power availability in Loudoun and Prince William counties has tightened, pushing hyperscale and colocation investment toward secondary Virginia markets with available land and transmission.
- β’The geography is deliberate. White Oak Technology Park sits roughly 90 to 110 miles from Data Center Alley, close enough to serve the same enterprise and federal customers but far enough to access land and power that NoVA can no longer easily offer.
- β’Submarine cable proximity adds latency value. Virginia Beach cable landings give Richmond-region campuses a credible story for transatlantic workloads.
- β’The federal compliance angle creates a moat. FISMA HIGH and FedRAMP certification is a long, expensive process. Iron Mountain's decision to certify RCH-3 at that level signals a deliberate play for defense and civilian agency contracts that commodity colocation cannot serve.
When a campus is designed for federal compliance from the ground up, it commands a staffing premium that goes far beyond typical critical-environment experience.
Infrastructure insight: compliance certifications change the hiring calculus
Most colocation builds require experienced MEP trades and a commissioning team comfortable with ANSI/TIA-942 or Uptime Tier documentation. A FISMA HIGH environment layers on top of that: every system change must be documented against NIST 800-53 controls, commissioning engineers must produce artifacts that satisfy federal auditors, and facilities technicians operate under change-management disciplines closer to a government SCIF than a commercial colocation floor. That means Iron Mountain will not simply be competing with Equinix and QTS for the same technician pool. It will be competing for people who have worked in federal data centers, cleared facilities, or defense-adjacent mission-critical environments, and that pool is considerably smaller.
What it means for the region's labor market
A four-building, 200 MW campus built in phases through 2029 is a sustained hiring event, not a single surge. Construction of RCH-1 is already underway, RCH-3 phases from August 2028 through April 2029, and the remaining buildings will follow on their own timelines. That sequencing means the region's trades will face overlapping demand for electricians, pipefitters, millwrights, and low-voltage specialists across multiple active fronts simultaneously. Richmond's industrial history produces real trades depth: paper, tobacco, chemical, and utility facilities have trained generations of skilled workers whose backgrounds transfer well to data center MEP work. Building trades unions are active on major industrial projects in the region, though commercial construction runs heavily open-shop, so Iron Mountain's delivery strategy will determine whether this campus is staffed through union agreements or large non-union contractors.
The sharper constraint is on the operations side. Commissioning engineers in the Richmond market are currently earning around $147,000 annually (ZipRecruiter/dcgeeks, 2026 figures). Critical facilities engineers run $117,000 to $147,000. Critical facilities technicians are around $89,000, and facilities technicians at approximately $54,000. Those figures reflect a national market tightened by the AI buildout cycle, and Henrico County competes directly with NoVA's data center cluster, which pulls the same profiles at similar or higher rates with shorter commutes for candidates already based in Loudoun or Prince William.
The single most actionable insight for staffing firms working this campus: Iron Mountain's federal compliance posture will favor candidates with prior experience in government or defense-related facilities, and documentation and QA/QC skills will carry a premium over general data center operational experience alone. Sourcing from Richmond's existing base of government-adjacent facilities, military contractors, and cleared-facility support staff is a more productive starting point than recycling candidates from purely commercial colocation backgrounds. For a full breakdown of roles, pay bands, and where to find qualified candidates in this market, see our guide to hiring data center talent in Henrico County. Sources: Iron Mountain Data Centers Richmond RCH-3 page, which provided primary project specifications; Iron Mountain Virginia overview; LinkedIn, Iron Mountain Data Centers campus progress post; Data Center Dynamics; Data Center Knowledge; and Colocation Scout.
Have a data center role to fill?
Send us the role Monday. Get three screened candidates by Friday, ready to meet your hiring team.
Read More Blog Posts
Hiring Data Center Talent in Henrico County, VA: Roles, Pay, and Where the People Actually Are
Iron Mountain is building a billion-dollar campus in Sandston, and the talent that campus needs is not sitting around waiting.
Hiring Data Center Talent Near Amarillo: Roles, Pay, and Where the People Actually Are in Carson County, TX
Carson County is about to have a data center hiring problem. InfraTech Capital announced a proposed $2.7 billion investment to develop a hyperscale-class campus spanning more than 5,000 acres in the Texas Panhandle, with